ACT – Adjudication Application Deadline Calculator

Building and Construction Industry (Security of Payment) Act 2009 (ACT), s 26

Calculate the deadline for lodging an adjudication application with an Authorised Nominating Authority (ANA) under the ACT SOP Act 2009. Three scenarios apply depending on whether a payment schedule was received and whether payment was made.

Scenario 1 — Payment schedule received, scheduled amount less than claimed (s 26(2)(a))

Lodge your adjudication application within 10 ACT business days of receiving the payment schedule.

Scenario 2 — Payment schedule received but amount not paid by due date (s 26(2)(b))

Lodge your adjudication application within 20 ACT business days after the due date for payment.

Scenario 3 — No payment schedule received, amount not paid (s 26(2)(c))

Serve a notice of intention to apply within 20 ACT business days of the due date, then apply within 10 ACT business days after the respondent's 5-business-day schedule period expires.

Adjudication Application Deadline Calculator
Select the scenario that applies to your payment claim under the ACT SOP Act 2009 (s 26)

Which scenario applies?

The date on which the respondent's payment schedule was received by you