CBEM Holdings Pty Ltd v Sunshine East Pty Ltd
Significant Court of Appeal decision addressing whether payment claims constitute representations of fact or opinion under the Australian Consumer Law, and confirming the right to recover overpayments made under SOPA through restitution claims.
The Facts
CBEM Holdings performed earthworks for Sunshine East on a Dural building project under a trade contract dated December 2021. CBEM submitted four payment claims (PC1-4), each endorsed under the Security of Payment Act, claiming it had completed 53% of the contracted works. The first three claims were approved by the construction manager (ASY), while the fourth was paid after no payment schedule was served in time. In November 2022, Sunshine East terminated the contract before CBEM had completed the works. The actual percentage of work performed was substantially less than claimed. Sunshine East had paid approximately $985,000 but expert evidence showed they were only liable for around $470,000.
Payment Claims: Representations of Fact or Opinion?
The primary judge found that CBEM's payment claims were misleading representations of FACT - that CBEM had actually performed the work detailed in the claims. CBEM argued they were representations of OPINION because assessing percentage completion requires evaluative judgment and the exercise of skill. The Court of Appeal agreed with CBEM on this point, holding that 'a representation that a task has been completed to a certain percentage is not generally one of fact because of the evaluative judgment required.' Further, where the maker of a representation of opinion reasonably and honestly holds that opinion, it will not be misleading or deceptive. This aligns with the principle in Global Sportsman v Mirror Newspapers that opinions based on genuine belief with reasonable grounds are not actionable under the ACL. However, this success on Ground 2 did not affect the ultimate outcome.
Restitution: Recovery of Overpayments Under SOPA
The Court upheld the respondents' claim for restitution based on the 'common money count' for money had and received. The Court identified two vitiating factors: (1) PC2 and PC3 were paid under a MISTAKEN BELIEF that the work claimed had actually been performed; and (2) PC4 was paid under COMPULSION of law (SOPA required payment when no payment schedule was served). Importantly, the Court confirmed that payments under SOPA are inherently provisional. Section 32 of the Act expressly contemplates that parties may seek restitution orders for amounts paid. The trade contract was construed to only entitle CBEM to payment for amounts 'properly claimed' - meaning claims that accurately identified work actually done. The contract did not give CBEM an unqualified right to retain payments simply because no dispute was notified within time.
The Decision
The Court of Appeal dismissed CBEM's appeal and ordered it to pay costs. While CBEM succeeded in establishing that its payment claims were representations of opinion rather than fact (Ground 2), this did not help its case because the restitution claim succeeded independently. The respondents were entitled to recover $452,961.44 - being the difference between what they paid and what CBEM was contractually entitled to receive for work actually performed. The Court emphasised that SOPA creates a 'pay now, argue later' regime, but this does not prevent subsequent recovery of overpayments. Restitutionary relief is available where there has been a total failure of consideration for unperformed work items, or where payment was made under mistake or compulsion.
Key Takeaways
- •Payment claims stating percentage completion are generally representations of OPINION, not fact, because they require evaluative judgment
- •An honest opinion genuinely held with reasonable grounds is not misleading or deceptive under the ACL - but lack of reasonable grounds may change this
- •SOPA payments are provisional - overpayments can be recovered through restitution claims even after the payment is made
- •Section 32 SOPA expressly preserves the right to seek restitution orders for amounts paid under the Act
- •Contracts requiring payment of amounts 'properly claimed' do not create an unqualified right to retain money paid
- •Keep accurate records of work performed - CBEM's failure to retain records hampered its defence on quantum
- •A restitution claim does not require pleading breach of contract - it only requires showing an overpayment was made
- •Construction managers approving claims does not prevent principals from later recovering overpayments