Victoria – Adjudication Application Deadline Calculator
Building and Construction Industry Security of Payment Act 2002 (Vic), s 18
Calculate the deadline for lodging an adjudication application with an Authorised Nominating Authority (ANA) under the Victorian SOP Act 2002. The deadline depends on which scenario applies.
Scenario A (s 18(1)): Payment schedule received — 10 Vic business days after receiving the schedule.
Scenario B (s 18(2)): No payment schedule — serve notice within 20 Vic business days of the due date (s 18(2)(a)), then apply within 10 Vic business days after the respondent's 5-business-day schedule period.
Which scenario applies?
August 2026
General Guide Only – Not Legal Advice
This calculator is a general guide only and is not legal advice. Timeframes can be affected by the specific terms of your construction contract, the precise method and timing of service, public holidays, and other factors. Always check the current legislation and seek professional advice. The operators of this site accept no liability for any loss or damage arising from reliance on this tool.
Check the Legislation
Calculations are based on the Building and Construction Industry Security of Payment Act 2002 (Vic), as amended. Reforms effective 15 April 2026 may affect your situation. Always verify deadlines against the current legislation.
Victorian Business Day Rules
Under the Vic SOP Act, a "business day" is any day that is not a Saturday, Sunday, Victorian public holiday, or any day in the period from 22 December to 10 January (inclusive). This is different from NSW, which only excludes 27–31 December.