Victoria – Security of Payment Calculators
Building and Construction Industry Security of Payment Act 2002 (Vic) — reforms effective 15 April 2026
Calculate statutory deadlines for payment schedules and payment due dates under the Victorian Building and Construction Industry Security of Payment Act 2002. All calculations use Victorian business day rules (excludes weekends, Victorian public holidays, and 22 December – 10 January).
Payment Schedule Deadlines
s 15 Vic SOP Act 2002
Due Dates for Payment
s 12 Vic SOP Act 2002
Victorian Business Days
22 Dec – 10 Jan shutdown
Business Day Definition
NSW SOP Act 1999
Excludes weekends, NSW public holidays, and 27–31 December
Vic SOP Act 2002
Excludes weekends, Victorian public holidays, and 22 December – 10 January (inclusive) — a longer shutdown period
Key Rule Differences
Payment Schedule Deadline Calculator
Under s 15 of the Vic SOP Act 2002, a payment schedule must be served within the time required by the construction contract, or 10 Victorian business days after the payment claim was served — whichever is earlier.
Contract vs. Statutory Deadlines
Under s 15 of the Vic SOP Act 2002, a payment schedule must be served within the period required by the contract or 10 business days after the payment claim is served — whichever is earlier. Always check your contract for any shorter period.
August 2026
Non-business days under Vic SOP Act 2002:
Weekends, Victorian public holidays, and 22 December – 10 January
Due Date for Payment Calculator
Under s 12 of the Vic SOP Act 2002, any contractual payment term later than 20 Victorian business days after service of the payment claim is of no effect. Where no payment term is specified, the default is 10 Victorian business days.
20 Business Day Statutory Cap (s 12)
Under s 12 of the Vic SOP Act 2002, any contractual payment term longer than 20 Vic business days after service of the payment claim is of no effect. If no payment terms are specified in the contract, the default is 10 Vic business days.
General Guide Only – Not Legal Advice
This calculator is a general guide only and is not legal advice. Timeframes can be affected by the specific terms of your construction contract, the precise method and timing of service, public holidays, and other factors. Always check the current legislation and seek professional advice. The operators of this site accept no liability for any loss or damage arising from reliance on this tool.
Check the Legislation
Calculations are based on the Building and Construction Industry Security of Payment Act 2002 (Vic), as amended. Reforms effective 15 April 2026 may affect your situation. Always verify deadlines against the current legislation.
Victorian Business Day Rules
Under the Vic SOP Act, a "business day" is any day that is not a Saturday, Sunday, Victorian public holiday, or any day in the period from 22 December to 10 January (inclusive). This is different from NSW, which only excludes 27–31 December.